General Standards

General Standards — 60 practice exam questions with instant feedback and cited explanations.

Practice Exams › License Exams › Certified Applicator › General Standards
Start practice — 60 questions →

Sample questions (showing 8 of 60)

On what cycle do pesticide applicator certifications expire in Tennessee?

Show answer Certifications follow a three-year cycle that began June 30, 2023, expiring on June 30 of every third year after that (rule .05(4)).

🔗 Source

Under Tennessee's continuing education schedule, how many CEUs must a C07 (Industrial, Institutional, Structural, and Health-Related Pest Control) applicator earn to recertify in lieu of testing?

Show answer Tennessee's recertification table assigns C07 the highest credit total at 21 CEUs, whereas most other commercial categories require only 12 or 18.

Under Tennessee's rules, by what point must charter renewal fees and materials be submitted to avoid an added late charge?

Show answer Renewals are due on or before July 1 of the year the charter expires, and a late charge under T.C.A. 43-1-703 applies only if fees or materials are not provided by July 16 following expiration (rule .03(5) and (5)(a)).

🔗 Source

In Tennessee, if a licensee fails to keep the applicator certification their pest control operator license depends on, what is needed before the license can be reissued?

Show answer Losing the underlying certification causes the license to expire and requires passing the exam for both the applicable certification and the license before it can be reissued (rule .04(6)).

🔗 Source

Under Tennessee's rules, who may make an application of a pesticide for which certification is required?

Show answer Tennessee bars applying certification-required pesticides unless the applicator is certified or works under the direct supervision of a certified person, and this rule does not relax stricter requirements found elsewhere in the chapter.

Under Tennessee's rules, what is the consequence when a charter holder's bonding or insurance lapses?

Show answer A lapse in bonding or insurance triggers immediate expiration of the charter, though the holder has a 30-day grace period to submit proof of valid coverage before a new charter is required (rule .03(5)(b)).

🔗 Source

Under Tennessee's recordkeeping rules, which two extra items must a restricted use pesticide application record include beyond the standard fields?

Show answer For restricted use pesticide applications, the record must additionally include the pesticide's EPA registration number and the time the application was made (rule .06(3)(k)).

🔗 Source

In Tennessee, what fraction of the required CEUs must a C07 applicator obtain through external trainings when recertifying by CEU accrual?

Show answer Applicators in most categories must earn at least half of their CEUs externally, but Tennessee holds C07 to a stricter standard requiring at least two-thirds from external trainings.

← All practice exams